Background
GNER contracted EWSR to provide strategic rescue services for its HST fleet operating out of London. The Class 67 locomotive was selected for the job because it is a high-speed diesel locomotive. However, the Class 67 has a combination coupler that does not interface with the coupler carried on the HST. So, ESG were asked to design, test and deliver a suitable adapter to connect the two locomotives.
Project Overview
Due to the restricted side clearance of the draw hook on the swinghead autocoupler, the current adapter (that fits a standard locomotive drawhook) did not fit. Initial design ideas investigated ways of modifying this adapter but were quickly replaced with one that interfaced with the knuckle coupler of the Class 66/67. Drawings were created on AutoCAD, and stresses calculated using MathCAD software. The main design restraints were; ensuring the component withstands the rated strength without any permanent set; is of low weight (for man-handling); ease of installation and manufacture; and low cost. Material selection formed a vital part in this process, and a high-alloy aluminium was finally selected. CAD Manufacturing Drawing
Testing

There was some initial testing of a lightly modified drawhook adapter, as currently used on the HST, but this proved to be fiddly to fit and, more importantly, was unstable in buff. It was clear that the best solution was to interface with the autocoupler on the 66/67 and a prototype was made and subject to controlled field testing using an HST trainset and a Class 67 (checking installation/fit, low speed curving, static pull etc). the couple was then subject to destructive proof testing on a tensile rig.

The coupler performed very well in all tests and met the proof tensile test requirement, it eventually failed when subject to an offset (5°) tensile load just above the rated value.

A second prototype was made and subject to more realistic field testing, hauling an HST set down the East Coast Main Line to London and back. During the test the loco speed and traction amps were monitored to ensure the coupler received the full tractive effort of the locomotive. After the test critical dimensions were rechecked to ensure there was no permanent set. The test was also an opportunity to gauge the opinion of ground staff into the ease of fit and installation of the adapter coupler.

Prototype Testing
Optimisation

Although, the coupler met the test criteria, it was decided to strengthen the component around the area of failure (the second pin joint) and the material section was increased around this feature.

The coupler was fitted with more robust locating chains and supplied with short extension hoses, following experience gained on test and the wishes of GNER ground staff.

Surface finish and chamfering details were added to the drawing, to improve the look and handleability of the coupler.

Finished Kit
Production & Delivery

ESG managed the production of over 20 adapter couplers, fitted safety labels, attached ancillary components and made up the extension hoses, so that a complete and final kit could be presented to the client. Spare parts and maintenance information (such as NDT) were also developed and supplied as part of the contract. ESG also managed the delivery and transportation logistics to ensure the client was supplied where and when agreed.

Productionisation
Key Features
  • Selection of materials to meet stringent strength and weight (man-handling) requirements
  • Full technical support for design and production units
  • Extensive testing in laboratory and on full HST sets out on the track
  • Comprehensive 'one-stop shop' solution for the client
  • Design compliant to latest Railway Group Standards and legislative regulations
  • Design to meet stringent cost and turn around timescales
Skills Profile
  • Material selection
  • In-field and rig testing
  • Project Management
  • Client liaison
  • Risk assessment
  • Technical documentation (spares and maintenance)